The Condamine to Braemar Pipeline (also known as the Braemar pipeline or the Braemar Linepack Connection) is a transmission pipeline located in southeast Queensland. The pipeline is owned and operated by Alinta Energy.
The pipeline is approximately 150km in length, and has a diameter of 406.4 mm.
The Condamine to Braemar Pipeline connects Alinta’s Braemar power station to the APA Group’s compressor station at Condamine.
The Condamine to Braemar Pipeline is currently a non-scheme pipeline, and is subject to the access regime for non-scheme pipelines under Chapter 6A of the NGL and Part 10 of the NGR. On 14 December 2017, the AER granted a five-year category 2 exemption under Part 10 of the NGR for the Condamine to Braemar Pipeline.
Construction on the pipeline was completed in March 2006.